Cabin Update: More T&G Progress

      I have a few pics for tonight on the great T&G adventure, as you can see we finished one wall minus final corner trim but thats the little stuff.

 The ugly in the middle is the rough frame out for the window and we are just butting all the T&G up to the window outline for now and we will complete that part when the window goes in and then trim, I did scratch my head for a minute and thought " What the heck an I gonna do here "
Two additional pics at different angles, now for the tough part someone needs to pick out a floor..

As always if there are any thoughts or comments please do not hesitate.

Follow Prepology on Twitter

Cabin Update: T&G Wall's and Ceiling

 Well the ceiling for the west bedroom is up and it is going to look very nice when it is trimmed and stained. This stuff is so much nicer than drywall and it add instant value 42 cents a square foot is well worth it.


We finally picked a pattern for the walls, we went with horizontal down to about forty inches from the deck and then we transitioned to a vertical but we went to the eight inch material that we also ordered. 










Here is a close up of the transition point and as you can see on the horizontal the tongue is down so where we transitioned to the vertical Piece I cut in a groove to accept the tongue to lock it in and it works very nice.

There is also an east bedroom and I am thinking about adding in some other accent pieces or designs so If anyone out there has any thoughts or ideas leave me a comment and ya never know.....


Have a good evening everyone.
Prepology

Follow Prepology on Twitter

Cabin Update: T&G Installation

 Evening everyone I have a short post for today but a really  good one, as promised we have some T&G up for today so you can get some idea what the ceilings will look like throughout the cabin. Shown here are the first seven rows.
We started the day off with some insulation and then transitioned into the T&G and this is where we ended up for the day at 12 rows or just about half of the room. We also plan on using some T&G for the walls as well but I wanted to get the ceiling done first and then play with the pattern for the walls. We will be adding more material all this week so you should get to see the progress pretty well and as always if there are any questions or comments please feel free to and I will get back to you.
Also for more post's on this build you can go to the update page here

Prepology

Follow Prepology on Twitter

Cabin Update: Data, Insulation and T&G

    Great day today as we had our first order of Tongue & Groove show up as well as the balance of our 4x8x1 sheets of Styrofoam. We also got out 44 bags of batts insulation in as well (R-11, R-19 and R-30) Needless to say that was a royal pain carrying almost half that insulation up two flights of stairs but it is all worth it.
 Here is a closer view of the T&G, what you see here is 1x6x16 and it is 1,500 square feet. I can't wait to install this material and we will be starting tomorrow as soon as we install a few more bags of batts insulation. We haven't decided on what color stain as of yet but it will most likely be a very light one. This T&G will be for the ceilings and we are also going to play around with it and see if we can find a nice pattern to use for the walls, drywall is strictly verboten here on this project and I totally agree as right now there is not one single piece here at all.
 We have also started pulling the data lines that will be for the satellite, internet as well as future telephone. The wire we are using is RG-6 for the satellite, Cat-5E for the internet ( we will also use wireless ) and CAT-3 for the telephone. We are running 2 of each to all three bedrooms and to the entertainment room on the first floor, we will also have a few other lines scattered to a few other areas but some locations have not been picked as of yet.




Kind of a bad picture here but this is one location where we will have an internet and telephone jack, across the room will be the RG-6 for the television.










Finally after we unloaded the truck and got some of the insulation up to the 3rd floor we dug right in and burned through about 4 bags of insulation (R-19 in the walls and R-30+4 in the ceiling) we still have a little to go but we will be working on the T&G but mid morning hopefully. As always if there are any questions or thoughts please feel free to comment and I will get back to you. You can also see additional posts on this cabin on the UPDATE PAGE.




Prepology

Follow Prepology on Twitter

     In response to the nasty weather that occurred this weekend I know more then a few may have been caught off guard by the event. I believe that having some type of weather alert radio is absolutely invaluable to keep informed of pending weather emergencies. Modern weather alert radios will monitor NOAA broadcasts ans with SAME technology they can be programmed to alert you in your specific county. For further information on this product as well as additional capabilities just click on the picture.